Assign Cable

Assign Cable

Summary

Each auto-routed cable run assigns a cable to the starting device and populates the cable data in the device properties. Cables can be reassigned as needed by using the Assign Run feature. For example, all runs originating from a load center can be populated on a schedule for that load center.

  • eVolve tab ⮞ Cabling panel ⮞ Assign Cable button

Usage

To Change/Add a Cabling Run Assignment
  1. From the eVolve ribbon, in the Cabling panel, click Assign Cable.
  2. From the drawing area, click the cable to reassign and then click the device to assign it.
  3. Repeat for additional devices or select Cancel to end the command.

Relevant Articles


How did we do?